Projects

CHEMICAL AND RADIOLOGICAL REMEDIATION

Industry: Manufacturing

Location: Northeast

Result: Sustainable Environment

Multi-Phase Remediation and Restoration Creates Pond, Wetlands, and Walking Trails

ENTACT is leading an extensive ecological restoration of more than 100 acres at a former industrial site that hosts several chemical manufacturers, a clay mining operation, and a disposal area for impacted soils and dredge spoils. The restoration plan aims to create a 14-acre open-water pond, 40 acres of wetland mitigation, 55 acres of upland enhancement, and nearly two miles of public walking trails and boardwalks. The project comprises multiple phases, detailed below:

Phase 1: Sediment Remediation
The initial phase focused on remediating impacted sediments from a five-acre lake, addressing contaminants such as benzaldehyde, bis (2-ethylhexyl) phthalate (BEHP), formaldehyde, and PCBs. The sediments varied in depths and were underlain by denser sands and clays. During Phase 1, ENTACT:

  • Drained and dewatered the lake
  • Constructed and operated a temporary water treatment system
  • Removed 30,000 cubic yards of contaminated sediment
  • Prepared the on-site consolidation area
  • Constructed a four-acre surface cover over the consolidation area
  • Imported 3,600 cubic yards of cap fill
  • Placed 3,600 cubic yards of topsoil and vegetation
  • Performed mitigation, seeding, and planting in disturbed areas, wetlands, and upland regions
  • Installed permanent stormwater features, including conveyance channels and aprons in the encroachment area and a concrete headwall in the lake

Phase 2: VOC and Radiological Remediation
The second phase targeted 23 acres impacted by VOCs, SVOCs, PCBs, pesticides, metals, and radiological waste (Ra-226, Th-232, and U-238). In Phase 2, ENTACT:

  • Assembled and operated a water pre-treatment and storage system
  • Targeted excavation of visually observed non-aqueous phase liquids (NAPL) impacted soil and sediment
  • Installed a barrier wall system using steel sheet piling, connected to existing structures
  • Prepared subgrade, including cutting/filling and material handling prior to the installation of soil upland surface covers and a low permeability geosynthetic cap
  • Installed a surface cover and low permeability cap systems
  • Installed NAPL recovery wells, a barrier wall, wetland piezometers, and amendment application wells
  • Performed waste and material management, including off-site transportation and disposal
  • Completed wetland restoration and mitigation
  • Installed permanent stormwater measures

Phase 3: Upland Remediation
During the third phase, ENTACT focused on the western uplands, completing the following key scope tasks. Our team:

  • Blended and capped soil exceeding radiological cleanup criteria
  • Placed cap fill material and topsoil within the forest land use area
  • Base grading and consolidation of excess soils
  • Restored wetland areas, including removal of fill materials, wetland surface cover application, invasive species management, reseeding, and planting to enhance upland and riparian habitats

Phase 4: Infrastructure and Habitat Development
The final phase encompassed the construction of:

  • Paved and gravel access roads, parking, and turn-around areas
  • A trail network featuring stone and asphalt paths, public gathering areas, and bird blinds
  • Boardwalks and overlook platforms, along with comprehensive site restoration

Auxier, a division of ENTACT, managed the radiological activities, coordinating with state regulators to establish project scope, applicable radiological release criteria, and the operation of an onsite radiological laboratory. During the project, Auxier:

  • Established a radiation safety program and fully staffed radiological laboratory onsite
  • Excavated a two-acre uranium-impacted area and shipped 6,000 tons of soil offsite for disposal at an RCRA subtitle C facility
  • Reused 45,000 tons of lightly impacted uranium soil onsite
  • Characterized adjacent TENORM-impacted wetlands to depths of 16 feet, with all activities monitored and managed

MARSSIM-based surveys are being used to demonstrate compliance with release criteria, and delicensing of the property is expected in late 2025.

Let’s work together

We want to hear about your project. Learn how we
deliver results with innovation.

Contact us

Three individuals in an office looking at project plans on a large wooden desk